Information
Premium Practice Questions
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 10 questions answered correctly
Your time:
Time has elapsed
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Answered
- Review
-
Question 1 of 10
1. Question
An incident ticket at a fintech lender is raised about Development of abatement project specifications during third-party risk. The report states that during a pre-acquisition audit of a regional operations center, the third-party environmental consultant provided a generic abatement plan for a 15,000-square-foot facility containing surfacing materials. The internal audit team must evaluate if the project specifications are sufficient to mitigate liability and health risks before the 30-day renovation window begins. Which element is most critical to include in the project specifications to ensure the abatement is legally defensible and technically sound?
Correct
Correct: Project specifications must be site-specific and rigorous to protect the organization from liability. Engineering controls, such as HEPA-filtered negative pressure units, are essential for containment. Furthermore, Transmission Electron Microscopy (TEM) is the superior analytical method for clearance because it can resolve the thinnest asbestos fibers that are invisible to Phase Contrast Microscopy (PCM), providing a higher level of assurance that the area is safe for re-occupancy.
Incorrect: The General Industry Standard is often less stringent than the Construction Standard (29 CFR 1926.1101), which is the primary regulation for abatement activities. Relying solely on PCM for clearance is a common cost-saving measure but is less technically sound than TEM in high-risk environments because PCM cannot distinguish between asbestos and non-asbestos fibers. Focusing on mineralogical varieties like actinolite to find ‘non-regulated’ loopholes is incorrect, as all six regulated asbestos minerals are subject to the same stringent requirements if they exceed 1% concentration in friable material.
Takeaway: Comprehensive abatement specifications must prioritize high-sensitivity clearance testing and specific engineering controls over generic regulatory references or cost-saving analytical methods.
Incorrect
Correct: Project specifications must be site-specific and rigorous to protect the organization from liability. Engineering controls, such as HEPA-filtered negative pressure units, are essential for containment. Furthermore, Transmission Electron Microscopy (TEM) is the superior analytical method for clearance because it can resolve the thinnest asbestos fibers that are invisible to Phase Contrast Microscopy (PCM), providing a higher level of assurance that the area is safe for re-occupancy.
Incorrect: The General Industry Standard is often less stringent than the Construction Standard (29 CFR 1926.1101), which is the primary regulation for abatement activities. Relying solely on PCM for clearance is a common cost-saving measure but is less technically sound than TEM in high-risk environments because PCM cannot distinguish between asbestos and non-asbestos fibers. Focusing on mineralogical varieties like actinolite to find ‘non-regulated’ loopholes is incorrect, as all six regulated asbestos minerals are subject to the same stringent requirements if they exceed 1% concentration in friable material.
Takeaway: Comprehensive abatement specifications must prioritize high-sensitivity clearance testing and specific engineering controls over generic regulatory references or cost-saving analytical methods.
-
Question 2 of 10
2. Question
Which safeguard provides the strongest protection when dealing with Personal Protective Equipment (PPE) for Asbestos Work? During an operational audit of a hazardous material abatement project, an internal auditor assesses the controls intended to prevent worker exposure to friable asbestos. While the project utilizes various forms of PPE, the auditor must determine which control most effectively ensures that respiratory equipment provides the intended level of protection against fiber inhalation.
Correct
Correct: Quantitative fit testing is the most critical safeguard because it provides an objective, numerical measure of how well a respirator fits the individual’s face. Since asbestos fibers are microscopic, even a minor gap in the seal of a respirator can lead to significant inhalation exposure, rendering the high-efficiency filters ineffective. Regulatory standards, such as those from OSHA, mandate fit testing to ensure the assigned protection factor (APF) of the respirator is actually achieved in practice.
Incorrect: While disposable coveralls with taped seams are essential for preventing skin contamination and the secondary spread of fibers, they do not mitigate the primary hazard of inhalation. Filter replacement schedules are a necessary maintenance control, but they are secondary to the integrity of the mask seal; a new filter cannot protect a worker if air bypasses it through a poor seal. Pre-entry safety briefings are administrative controls that improve worker knowledge but do not provide a physical or technical verification of the equipment’s performance.
Takeaway: The effectiveness of respiratory PPE in asbestos environments is primarily dependent on the integrity of the face-to-mask seal, which must be verified through individual quantitative fit testing.
Incorrect
Correct: Quantitative fit testing is the most critical safeguard because it provides an objective, numerical measure of how well a respirator fits the individual’s face. Since asbestos fibers are microscopic, even a minor gap in the seal of a respirator can lead to significant inhalation exposure, rendering the high-efficiency filters ineffective. Regulatory standards, such as those from OSHA, mandate fit testing to ensure the assigned protection factor (APF) of the respirator is actually achieved in practice.
Incorrect: While disposable coveralls with taped seams are essential for preventing skin contamination and the secondary spread of fibers, they do not mitigate the primary hazard of inhalation. Filter replacement schedules are a necessary maintenance control, but they are secondary to the integrity of the mask seal; a new filter cannot protect a worker if air bypasses it through a poor seal. Pre-entry safety briefings are administrative controls that improve worker knowledge but do not provide a physical or technical verification of the equipment’s performance.
Takeaway: The effectiveness of respiratory PPE in asbestos environments is primarily dependent on the integrity of the face-to-mask seal, which must be verified through individual quantitative fit testing.
-
Question 3 of 10
3. Question
A regulatory inspection at a credit union focuses on Design and construction of containment barriers (e.g., poly sheeting, zippers, negative air machines) in the context of change management. The examiner notes that during a recent HVAC system upgrade involving the removal of asbestos-containing thermal system insulation, the internal audit team identified inconsistencies in the containment monitoring logs. Specifically, the project documentation for the 72-hour abatement window lacks evidence of active pressure verification. Which of the following represents the most effective engineering control to ensure the containment barrier prevents the release of airborne fibers into the rest of the facility?
Correct
Correct: The primary engineering control for asbestos containment is the maintenance of negative air pressure. A minimum of -0.02 inches of water gauge ensures that air flows into the containment area in the event of a minor breach, preventing fiber migration. A continuous-reading manometer (pressure recorder) provides the necessary documentation and audit trail to prove the control was functioning throughout the entire abatement period.
Incorrect: While 4-mil sheeting is used, 6-mil is the standard for critical barriers and floors to prevent punctures; furthermore, sheeting alone is a passive barrier and does not account for air movement. Visual inspections are necessary but are considered administrative controls that cannot detect microscopic fiber leaks or pressure drops in real-time. Providing only two air changes per hour is generally insufficient, as industry standards and regulations typically require at least four air changes per hour to ensure adequate filtration and negative pressure.
Takeaway: The most critical engineering control for asbestos containment is the maintenance and continuous monitoring of negative air pressure to ensure inward airflow and prevent environmental contamination.
Incorrect
Correct: The primary engineering control for asbestos containment is the maintenance of negative air pressure. A minimum of -0.02 inches of water gauge ensures that air flows into the containment area in the event of a minor breach, preventing fiber migration. A continuous-reading manometer (pressure recorder) provides the necessary documentation and audit trail to prove the control was functioning throughout the entire abatement period.
Incorrect: While 4-mil sheeting is used, 6-mil is the standard for critical barriers and floors to prevent punctures; furthermore, sheeting alone is a passive barrier and does not account for air movement. Visual inspections are necessary but are considered administrative controls that cannot detect microscopic fiber leaks or pressure drops in real-time. Providing only two air changes per hour is generally insufficient, as industry standards and regulations typically require at least four air changes per hour to ensure adequate filtration and negative pressure.
Takeaway: The most critical engineering control for asbestos containment is the maintenance and continuous monitoring of negative air pressure to ensure inward airflow and prevent environmental contamination.
-
Question 4 of 10
4. Question
Serving as operations manager at a private bank, you are called to advise on Wet removal methods (e.g., wetting agents, misting) during sanctions screening. The briefing a board risk appetite review pack highlights that the bank is simultaneously upgrading its physical security and environmental controls at the main branch. During the audit of the environmental remediation project, the team is assessing the controls used to prevent the aerosolization of asbestos fibers. Which of the following best describes the primary function of a surfactant (wetting agent) when applied to asbestos-containing materials during the removal process?
Correct
Correct: Surfactants are added to water to lower its surface tension, creating amended water that can penetrate porous asbestos-containing materials more effectively than plain water. This ensures that the fibers are thoroughly wetted and weighted down, which is a critical control for preventing the release of friable fibers into the air during physical disturbance or removal.
Incorrect
Correct: Surfactants are added to water to lower its surface tension, creating amended water that can penetrate porous asbestos-containing materials more effectively than plain water. This ensures that the fibers are thoroughly wetted and weighted down, which is a critical control for preventing the release of friable fibers into the air during physical disturbance or removal.
-
Question 5 of 10
5. Question
The compliance framework at a credit union is being updated to address Third-party air monitoring and quality assurance as part of control testing. A challenge arises because the internal audit team discovers that the environmental consultant hired to perform final clearance air sampling for a 12-week renovation project is a subsidiary of the same parent company as the abatement contractor. The Chief Audit Executive (CAE) must evaluate the impact of this relationship on the reliability of the air quality data. Which of the following actions best ensures the integrity of the quality assurance process in this scenario?
Correct
Correct: Independence is a fundamental principle of quality assurance in asbestos abatement. If the monitoring firm and the contractor share a parent company, there is a significant conflict of interest that undermines the objectivity of the clearance testing. Engaging a truly independent third party is the only way to ensure the results are unbiased, legally defensible, and compliant with best practices for environmental safety.
Incorrect: Increasing sampling frequency does not address the underlying conflict of interest or the risk of biased reporting. Relying on an affidavit is an administrative control that provides no objective evidence of safety or technical accuracy. Internal audit observation is insufficient because auditors typically lack the technical expertise and specialized equipment required to validate the scientific integrity of asbestos fiber counting and laboratory analysis.
Takeaway: To ensure the validity of asbestos clearance testing, the air monitoring entity must remain completely independent of the abatement contractor to prevent conflicts of interest and ensure objective results.
Incorrect
Correct: Independence is a fundamental principle of quality assurance in asbestos abatement. If the monitoring firm and the contractor share a parent company, there is a significant conflict of interest that undermines the objectivity of the clearance testing. Engaging a truly independent third party is the only way to ensure the results are unbiased, legally defensible, and compliant with best practices for environmental safety.
Incorrect: Increasing sampling frequency does not address the underlying conflict of interest or the risk of biased reporting. Relying on an affidavit is an administrative control that provides no objective evidence of safety or technical accuracy. Internal audit observation is insufficient because auditors typically lack the technical expertise and specialized equipment required to validate the scientific integrity of asbestos fiber counting and laboratory analysis.
Takeaway: To ensure the validity of asbestos clearance testing, the air monitoring entity must remain completely independent of the abatement contractor to prevent conflicts of interest and ensure objective results.
-
Question 6 of 10
6. Question
In assessing competing strategies for Purpose and types of air monitoring (e.g., baseline, in-process, clearance), what distinguishes the best option? An internal auditor is reviewing the environmental health and safety (EHS) controls for a large-scale asbestos abatement project within a corporate headquarters. The auditor is evaluating the adequacy of the air monitoring program to ensure it mitigates the risk of fiber release into occupied areas and confirms the site is safe for general re-occupancy.
Correct
Correct: The most comprehensive strategy involves three distinct phases: baseline monitoring to establish a reference point, daily in-process area monitoring to verify the integrity of the containment and protect building occupants, and clearance sampling. Using Transmission Electron Microscopy (TEM) for clearance is the superior choice for indoor environments as it can distinguish asbestos fibers from other materials and detect much smaller fibers than Phase Contrast Microscopy (PCM), providing a higher level of safety assurance for re-occupancy.
Incorrect: Relying solely on PCM is insufficient for clearance in many jurisdictions because it cannot distinguish fiber types and has a higher detection limit. Focusing only on personal monitoring ignores the risk to the surrounding environment and occupants. Visual inspection, while a necessary first step, cannot detect microscopic airborne fibers and is not a substitute for air sampling. In-process monitoring must be proactive and continuous rather than reactive to suspected breaches. Clearance sampling on wet surfaces is invalid as moisture suppresses fiber release, leading to false-negative results.
Takeaway: A robust asbestos air monitoring program must include baseline, daily area, and high-sensitivity clearance testing to ensure containment integrity and verify that the area is safe for the public.
Incorrect
Correct: The most comprehensive strategy involves three distinct phases: baseline monitoring to establish a reference point, daily in-process area monitoring to verify the integrity of the containment and protect building occupants, and clearance sampling. Using Transmission Electron Microscopy (TEM) for clearance is the superior choice for indoor environments as it can distinguish asbestos fibers from other materials and detect much smaller fibers than Phase Contrast Microscopy (PCM), providing a higher level of safety assurance for re-occupancy.
Incorrect: Relying solely on PCM is insufficient for clearance in many jurisdictions because it cannot distinguish fiber types and has a higher detection limit. Focusing only on personal monitoring ignores the risk to the surrounding environment and occupants. Visual inspection, while a necessary first step, cannot detect microscopic airborne fibers and is not a substitute for air sampling. In-process monitoring must be proactive and continuous rather than reactive to suspected breaches. Clearance sampling on wet surfaces is invalid as moisture suppresses fiber release, leading to false-negative results.
Takeaway: A robust asbestos air monitoring program must include baseline, daily area, and high-sensitivity clearance testing to ensure containment integrity and verify that the area is safe for the public.
-
Question 7 of 10
7. Question
Which consideration is most important when selecting an approach to Fit testing and maintenance of respirators? During an internal audit of a construction firm specializing in asbestos abatement, the auditor is reviewing the effectiveness of the Respiratory Protection Program (RPP). The audit focuses on whether the current fit testing procedures and maintenance cycles are sufficient to protect workers from airborne chrysotile fibers. In evaluating the adequacy of these controls, which of the following must be the primary focus?
Correct
Correct: According to OSHA’s Respiratory Protection Standard (29 CFR 1910.134), which is the benchmark for asbestos abatement safety, fit testing must be specific to the equipment used. Because different respirator models and sizes have different sealing surfaces and dimensions, a fit test is only valid for the specific make, model, and size tested. From an audit perspective, this is a critical control to ensure the Assigned Protection Factor (APF) is actually achieved for the individual worker.
Incorrect: Qualitative fit testing is not inherently superior; in fact, quantitative fit testing provides an objective numerical measure of leakage and is required for certain high-protection respirators. While frequent filter replacement is a safe practice, it is a maintenance detail that does not address the fundamental requirement of ensuring a proper seal. A user seal check is a mandatory procedure to be performed by the wearer before each entry into a contaminated zone, but it is a subjective check and never a regulatory substitute for a formal annual fit test.
Takeaway: A respirator fit test is only valid for the specific make, model, and size of the equipment that the employee will use in the field to ensure a proper seal.
Incorrect
Correct: According to OSHA’s Respiratory Protection Standard (29 CFR 1910.134), which is the benchmark for asbestos abatement safety, fit testing must be specific to the equipment used. Because different respirator models and sizes have different sealing surfaces and dimensions, a fit test is only valid for the specific make, model, and size tested. From an audit perspective, this is a critical control to ensure the Assigned Protection Factor (APF) is actually achieved for the individual worker.
Incorrect: Qualitative fit testing is not inherently superior; in fact, quantitative fit testing provides an objective numerical measure of leakage and is required for certain high-protection respirators. While frequent filter replacement is a safe practice, it is a maintenance detail that does not address the fundamental requirement of ensuring a proper seal. A user seal check is a mandatory procedure to be performed by the wearer before each entry into a contaminated zone, but it is a subjective check and never a regulatory substitute for a formal annual fit test.
Takeaway: A respirator fit test is only valid for the specific make, model, and size of the equipment that the employee will use in the field to ensure a proper seal.
-
Question 8 of 10
8. Question
In your capacity as privacy officer at an audit firm, you are handling Principles of negative air pressure containment during periodic review. A colleague forwards you a whistleblower report showing that during the recent abatement of floor tiles in the firm’s data center, the contractor’s containment barriers appeared to lose their inward curvature during peak HVAC operation hours. The report suggests that the pressure monitoring system was frequently bypassed to avoid alarms. When reviewing the project’s environmental logs to determine if a breach of containment occurred, which of the following conditions would confirm that the negative air pressure system failed to meet standard safety principles?
Correct
Correct: The industry standard for asbestos containment, as established by regulatory bodies like OSHA and the EPA, requires a minimum negative pressure differential of -0.02 inches of water column relative to the outside area. A reading of -0.01 inches is less negative than the required threshold, indicating that the inward pull of air is insufficient to reliably prevent the escape of airborne fibers through microscopic gaps or during worker ingress/egress.
Incorrect: Failing to change pre-filters on a specific 24-hour schedule is a maintenance deficiency but does not inherently prove a failure of the pressure differential if the machines are still pulling sufficient air. Using flexible tubing for exhaust is a standard and acceptable practice in temporary abatement setups and does not violate the principles of negative pressure. Exceeding the specified air changes per hour (ACH) is a measure of ventilation volume and air filtration frequency, which generally enhances safety rather than indicating a containment failure.
Takeaway: Effective asbestos containment relies on maintaining a continuous negative pressure differential of at least -0.02 inches of water column to ensure air only flows into the contaminated zone.
Incorrect
Correct: The industry standard for asbestos containment, as established by regulatory bodies like OSHA and the EPA, requires a minimum negative pressure differential of -0.02 inches of water column relative to the outside area. A reading of -0.01 inches is less negative than the required threshold, indicating that the inward pull of air is insufficient to reliably prevent the escape of airborne fibers through microscopic gaps or during worker ingress/egress.
Incorrect: Failing to change pre-filters on a specific 24-hour schedule is a maintenance deficiency but does not inherently prove a failure of the pressure differential if the machines are still pulling sufficient air. Using flexible tubing for exhaust is a standard and acceptable practice in temporary abatement setups and does not violate the principles of negative pressure. Exceeding the specified air changes per hour (ACH) is a measure of ventilation volume and air filtration frequency, which generally enhances safety rather than indicating a containment failure.
Takeaway: Effective asbestos containment relies on maintaining a continuous negative pressure differential of at least -0.02 inches of water column to ensure air only flows into the contaminated zone.
-
Question 9 of 10
9. Question
Which approach is most appropriate when applying On-site supervision and quality control in a real-world setting? During an internal audit of a high-scale asbestos abatement project involving the removal of friable amosite from a facility’s HVAC system, the auditor evaluates the effectiveness of the contractor’s quality management system and the supervisor’s role in mitigating exposure risks.
Correct
Correct: Continuous monitoring is the gold standard for on-site supervision in asbestos abatement. Daily visual inspections ensure that containment barriers remain intact and that negative pressure is maintained, preventing the migration of fibers. Real-time air monitoring provides immediate feedback on the effectiveness of engineering controls, and verifying decontamination procedures ensures that workers do not transport fibers outside the regulated area. This proactive approach is consistent with OSHA and EPA NESHAP requirements for managing high-risk friable asbestos removal.
Incorrect: Relying only on final clearance sampling is a reactive approach that does not account for potential exposures or containment failures that may have occurred during the work. Delegating the oversight of critical safety systems like HEPA filtration to workers without direct supervisory verification creates a risk of equipment failure or improper maintenance. Weekly random visits are insufficient for high-risk abatement projects where site conditions and fiber concentrations can change rapidly, requiring constant vigilance to ensure regulatory compliance and safety.
Takeaway: Effective quality control in asbestos abatement requires proactive, continuous oversight of containment integrity, air quality, and decontamination protocols to mitigate risks in real-time.
Incorrect
Correct: Continuous monitoring is the gold standard for on-site supervision in asbestos abatement. Daily visual inspections ensure that containment barriers remain intact and that negative pressure is maintained, preventing the migration of fibers. Real-time air monitoring provides immediate feedback on the effectiveness of engineering controls, and verifying decontamination procedures ensures that workers do not transport fibers outside the regulated area. This proactive approach is consistent with OSHA and EPA NESHAP requirements for managing high-risk friable asbestos removal.
Incorrect: Relying only on final clearance sampling is a reactive approach that does not account for potential exposures or containment failures that may have occurred during the work. Delegating the oversight of critical safety systems like HEPA filtration to workers without direct supervisory verification creates a risk of equipment failure or improper maintenance. Weekly random visits are insufficient for high-risk abatement projects where site conditions and fiber concentrations can change rapidly, requiring constant vigilance to ensure regulatory compliance and safety.
Takeaway: Effective quality control in asbestos abatement requires proactive, continuous oversight of containment integrity, air quality, and decontamination protocols to mitigate risks in real-time.
-
Question 10 of 10
10. Question
Working as the risk manager for an investment firm, you encounter a situation involving Decontamination Procedures during gifts and entertainment. Upon examining a transaction monitoring alert, you discover that a facility manager at a subsidiary company accepted luxury travel vouchers from an asbestos removal contractor. A follow-up review of the contractor’s operational logs for a recent abatement project indicates that the mandatory three-stage decontamination sequence was bypassed, with personnel moving directly from the equipment room (dirty room) to the clean room. Which of the following represents the most significant internal control failure regarding the decontamination process in this scenario?
Correct
Correct: The shower stage is the critical middle component of a three-stage decontamination unit. Its primary function is to wet down and wash away asbestos fibers from the worker’s protective clothing and skin. By bypassing this stage and moving directly from the ‘dirty’ equipment room to the ‘clean’ room, the contractor allows for the mechanical transport of hazardous fibers into the clean environment, posing a significant health risk and violating standard abatement protocols.
Incorrect: The lack of a secondary HEPA filter in the clean room is not the primary failure, as the clean room is intended to remain uncontaminated through the use of the shower. While water filtration documentation is a regulatory requirement for environmental protection, it does not address the immediate risk of fiber migration on personnel. Third-party industrial hygienists typically perform area inspections and clearance testing rather than monitoring every individual worker’s transition through the decontamination unit.
Takeaway: The shower stage in a decontamination unit is the essential control for preventing the migration of asbestos fibers from the work area to the clean environment.
Incorrect
Correct: The shower stage is the critical middle component of a three-stage decontamination unit. Its primary function is to wet down and wash away asbestos fibers from the worker’s protective clothing and skin. By bypassing this stage and moving directly from the ‘dirty’ equipment room to the ‘clean’ room, the contractor allows for the mechanical transport of hazardous fibers into the clean environment, posing a significant health risk and violating standard abatement protocols.
Incorrect: The lack of a secondary HEPA filter in the clean room is not the primary failure, as the clean room is intended to remain uncontaminated through the use of the shower. While water filtration documentation is a regulatory requirement for environmental protection, it does not address the immediate risk of fiber migration on personnel. Third-party industrial hygienists typically perform area inspections and clearance testing rather than monitoring every individual worker’s transition through the decontamination unit.
Takeaway: The shower stage in a decontamination unit is the essential control for preventing the migration of asbestos fibers from the work area to the clean environment.