Quiz-summary
0 of 8 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
Information
Premium Practice Questions
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 8 questions answered correctly
Your time:
Time has elapsed
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- Answered
- Review
-
Question 1 of 8
1. Question
Which characterization of Submittals and Shop Drawings is most accurate for Certified Associate Construction Manager (CACM)? During the execution phase of a multi-story healthcare facility, the Construction Manager (CM) is coordinating the flow of technical data between the mechanical subcontractor and the Architect of Record. The subcontractor has provided detailed diagrams illustrating the specific assembly of the custom air handling units.
Correct
Correct: Submittals and shop drawings are the contractor’s way of showing how they intend to carry out the design. The Construction Manager facilitates this process, but the design professional (Architect or Engineer) must review them to ensure they conform to the design concept and the requirements of the contract documents. This process occurs before fabrication or installation to prevent costly errors.
Incorrect: The assertion that submittals supersede original specifications is incorrect because submittals are not contract documents and cannot change the contract requirements without a formal change order. The idea that they are primarily for brand selection is incorrect as equipment brands should generally be specified or approved during the procurement planning phase. Finally, shop drawings are not as-built drawings; as-builts record the actual installation after the fact, whereas shop drawings are prepared before installation.
Takeaway: Submittals and shop drawings are quality control tools used to verify that the contractor’s planned execution aligns with the design intent before work begins.
Incorrect
Correct: Submittals and shop drawings are the contractor’s way of showing how they intend to carry out the design. The Construction Manager facilitates this process, but the design professional (Architect or Engineer) must review them to ensure they conform to the design concept and the requirements of the contract documents. This process occurs before fabrication or installation to prevent costly errors.
Incorrect: The assertion that submittals supersede original specifications is incorrect because submittals are not contract documents and cannot change the contract requirements without a formal change order. The idea that they are primarily for brand selection is incorrect as equipment brands should generally be specified or approved during the procurement planning phase. Finally, shop drawings are not as-built drawings; as-builts record the actual installation after the fact, whereas shop drawings are prepared before installation.
Takeaway: Submittals and shop drawings are quality control tools used to verify that the contractor’s planned execution aligns with the design intent before work begins.
-
Question 2 of 8
2. Question
An escalation from the front office at a mid-sized retail bank concerns Procurement Ethics and Compliance during gifts and entertainment. The team reports that a primary contractor bidding on the bank’s regional branch expansion project has offered the lead procurement officer an all-expenses-paid trip to an international construction technology summit. The estimated value of the trip is $2,500, significantly exceeding the bank’s internal gift policy limit of $100. The procurement officer claims the trip is essential for evaluating the contractor’s technical capabilities before the contract award. Which action best aligns with professional ethics and procurement compliance?
Correct
Correct: Declining the invitation is the only action that fully adheres to the bank’s established gift threshold and prevents the appearance of a conflict of interest during an active procurement cycle. Recording the offer in a formal register ensures an audit trail and demonstrates a commitment to transparency, which is vital for maintaining the integrity of the bidding process.
Incorrect: Reimbursing the contractor for travel does not remove the ethical risk associated with accepting a high-value invitation from a bidder during a live tender. Recusal from only one committee is insufficient as the officer still maintains influence over the financial aspects of the procurement. Bringing a third-party consultant does not mitigate the violation of the internal gift policy or the potential for perceived bias created by the contractor’s hospitality.
Takeaway: To maintain procurement integrity, any gift or entertainment offer that exceeds established thresholds or occurs during a live bidding process must be declined and formally documented.
Incorrect
Correct: Declining the invitation is the only action that fully adheres to the bank’s established gift threshold and prevents the appearance of a conflict of interest during an active procurement cycle. Recording the offer in a formal register ensures an audit trail and demonstrates a commitment to transparency, which is vital for maintaining the integrity of the bidding process.
Incorrect: Reimbursing the contractor for travel does not remove the ethical risk associated with accepting a high-value invitation from a bidder during a live tender. Recusal from only one committee is insufficient as the officer still maintains influence over the financial aspects of the procurement. Bringing a third-party consultant does not mitigate the violation of the internal gift policy or the potential for perceived bias created by the contractor’s hospitality.
Takeaway: To maintain procurement integrity, any gift or entertainment offer that exceeds established thresholds or occurs during a live bidding process must be declined and formally documented.
-
Question 3 of 8
3. Question
The risk committee at a private bank is debating standards for Functional Analysis as part of onboarding. The central issue is that the bank is initiating a multi-year facility expansion, and the committee must decide how to evaluate the project’s scope during the definition phase. A proposal has been made to utilize a function-oriented approach to distinguish between essential requirements and optional features before finalizing the project charter. Within the framework of project definition and feasibility, which of the following best describes the primary purpose of this Functional Analysis?
Correct
Correct: Functional Analysis is a systematic process used during project definition and value engineering to identify the functions of a product or service. By focusing on what a project element must do (its function) rather than what it is (its physical design), the project team can ensure that the necessary performance is achieved at the lowest overall cost. This is critical during the feasibility and definition stages to align the project scope with the business case and avoid unnecessary expenditures.
Incorrect: Decomposing deliverables into work packages is the primary objective of creating a Work Breakdown Structure (WBS), which occurs after the scope has been defined. Identifying and categorizing stakeholders is the goal of Stakeholder Analysis, which focuses on communication and engagement rather than functional requirements. Establishing a schedule baseline is part of the Schedule Development process, which relies on the outputs of functional and scope analysis but does not define the functions themselves.
Takeaway: Functional Analysis prioritizes essential performance requirements over specific design solutions to optimize value and cost-efficiency during the project definition phase.
Incorrect
Correct: Functional Analysis is a systematic process used during project definition and value engineering to identify the functions of a product or service. By focusing on what a project element must do (its function) rather than what it is (its physical design), the project team can ensure that the necessary performance is achieved at the lowest overall cost. This is critical during the feasibility and definition stages to align the project scope with the business case and avoid unnecessary expenditures.
Incorrect: Decomposing deliverables into work packages is the primary objective of creating a Work Breakdown Structure (WBS), which occurs after the scope has been defined. Identifying and categorizing stakeholders is the goal of Stakeholder Analysis, which focuses on communication and engagement rather than functional requirements. Establishing a schedule baseline is part of the Schedule Development process, which relies on the outputs of functional and scope analysis but does not define the functions themselves.
Takeaway: Functional Analysis prioritizes essential performance requirements over specific design solutions to optimize value and cost-efficiency during the project definition phase.
-
Question 4 of 8
4. Question
What factors should be weighed when choosing between alternatives for Life Cycle Assessment (LCA)? A construction manager is evaluating two different structural systems for a new commercial office building during the feasibility phase. To ensure a comprehensive sustainability profile, the manager must look beyond initial capital costs and consider the long-term environmental footprint. When conducting this comparative analysis, which set of criteria is most critical for ensuring a valid and standardized assessment of the alternatives?
Correct
Correct: In Life Cycle Assessment (LCA), a valid comparison between alternatives requires a standardized ‘functional unit’ (e.g., providing a specific load-bearing capacity over a 50-year lifespan) to ensure an apples-to-apples comparison. System boundaries must be equivalent so that one alternative isn’t unfairly advantaged by excluding stages like end-of-life disposal or maintenance. Finally, selecting relevant impact categories ensures the assessment addresses the specific environmental goals of the project, such as carbon footprint or water scarcity.
Incorrect: Focusing on procurement lead times and labor availability addresses project logistics and scheduling rather than environmental life cycle impacts. Aesthetic preferences and tenant leasing are critical for project success and stakeholder management but do not constitute the scientific basis of an LCA. While LEED points and construction speed are important project metrics, they do not provide the methodological framework (functional units and boundaries) necessary to conduct a scientifically sound comparative LCA.
Takeaway: A valid comparative Life Cycle Assessment must utilize a standardized functional unit and consistent system boundaries to ensure environmental impacts are measured accurately across all alternatives.
Incorrect
Correct: In Life Cycle Assessment (LCA), a valid comparison between alternatives requires a standardized ‘functional unit’ (e.g., providing a specific load-bearing capacity over a 50-year lifespan) to ensure an apples-to-apples comparison. System boundaries must be equivalent so that one alternative isn’t unfairly advantaged by excluding stages like end-of-life disposal or maintenance. Finally, selecting relevant impact categories ensures the assessment addresses the specific environmental goals of the project, such as carbon footprint or water scarcity.
Incorrect: Focusing on procurement lead times and labor availability addresses project logistics and scheduling rather than environmental life cycle impacts. Aesthetic preferences and tenant leasing are critical for project success and stakeholder management but do not constitute the scientific basis of an LCA. While LEED points and construction speed are important project metrics, they do not provide the methodological framework (functional units and boundaries) necessary to conduct a scientifically sound comparative LCA.
Takeaway: A valid comparative Life Cycle Assessment must utilize a standardized functional unit and consistent system boundaries to ensure environmental impacts are measured accurately across all alternatives.
-
Question 5 of 8
5. Question
Which statement most accurately reflects Payment and Performance Guarantees for Certified Associate Construction Manager (CACM) in practice? During the procurement planning phase of a large-scale municipal infrastructure project, the Construction Manager is evaluating risk mitigation strategies regarding contractor default and the potential for non-payment of lower-tier vendors.
Correct
Correct: In construction management, performance bonds protect the owner by ensuring the contract is completed if the contractor defaults. Payment bonds protect the owner from legal encumbrances, such as mechanic’s liens, by guaranteeing that subcontractors and suppliers are paid for their labor and materials.
Incorrect: The suggestion that performance bonds cover all delays regardless of cause is incorrect, as they specifically address contractor default; furthermore, payment bonds protect subcontractors, not the prime contractor’s payments from the owner. Professional liability insurance covers errors and omissions and does not replace the risk mitigation provided by bonds. The Construction Manager does not act as a surety; bonds are issued by specialized third-party surety companies.
Takeaway: Performance bonds guarantee contract completion while payment bonds protect against liens by ensuring lower-tier vendors are paid.
Incorrect
Correct: In construction management, performance bonds protect the owner by ensuring the contract is completed if the contractor defaults. Payment bonds protect the owner from legal encumbrances, such as mechanic’s liens, by guaranteeing that subcontractors and suppliers are paid for their labor and materials.
Incorrect: The suggestion that performance bonds cover all delays regardless of cause is incorrect, as they specifically address contractor default; furthermore, payment bonds protect subcontractors, not the prime contractor’s payments from the owner. Professional liability insurance covers errors and omissions and does not replace the risk mitigation provided by bonds. The Construction Manager does not act as a surety; bonds are issued by specialized third-party surety companies.
Takeaway: Performance bonds guarantee contract completion while payment bonds protect against liens by ensuring lower-tier vendors are paid.
-
Question 6 of 8
6. Question
Your team is drafting a policy on Construction Project Legal Framework and Compliance as part of transaction monitoring for a private bank. A key unresolved point is how to validate that the General Contractor (GC) has properly mitigated the risk of mechanic’s liens during the project execution phase. The bank requires a specific control to be triggered for every progress payment request exceeding $500,000 to ensure the bank’s security interest in the property remains senior to any potential subcontractor claims. Which document or process provides the most robust legal assurance that subcontractors have been paid and have waived their right to file a lien against the property for the work covered in a specific billing period?
Correct
Correct: Lien waivers are the primary legal instrument used in construction to provide evidence that a subcontractor or supplier has received payment and, in exchange, gives up their right to file a lien against the property. In the context of a bank’s transaction monitoring and risk management, requiring these waivers ensures that the bank’s collateral (the property) is not encumbered by third-party claims, which could otherwise take priority over the bank’s mortgage in many jurisdictions.
Incorrect: A Performance and Payment Bond protects the owner against contractor default but does not automatically prevent the filing of liens or provide evidence of payment for a specific billing cycle. A notarized affidavit from the General Contractor is a self-representation and does not legally bind the subcontractors who actually hold the lien rights. A Certificate of Substantial Completion is a project management milestone indicating the building is ready for its intended use, but it does not address the financial discharge of labor and material costs or the legal release of claims.
Takeaway: Lien waivers are the essential legal mechanism for ensuring that progress payments result in the discharge of potential claims against a property’s title.
Incorrect
Correct: Lien waivers are the primary legal instrument used in construction to provide evidence that a subcontractor or supplier has received payment and, in exchange, gives up their right to file a lien against the property. In the context of a bank’s transaction monitoring and risk management, requiring these waivers ensures that the bank’s collateral (the property) is not encumbered by third-party claims, which could otherwise take priority over the bank’s mortgage in many jurisdictions.
Incorrect: A Performance and Payment Bond protects the owner against contractor default but does not automatically prevent the filing of liens or provide evidence of payment for a specific billing cycle. A notarized affidavit from the General Contractor is a self-representation and does not legally bind the subcontractors who actually hold the lien rights. A Certificate of Substantial Completion is a project management milestone indicating the building is ready for its intended use, but it does not address the financial discharge of labor and material costs or the legal release of claims.
Takeaway: Lien waivers are the essential legal mechanism for ensuring that progress payments result in the discharge of potential claims against a property’s title.
-
Question 7 of 8
7. Question
A new business initiative at an audit firm requires guidance on Health and Wellness Programs as part of regulatory inspection. The proposal raises questions about how a construction management firm should integrate these programs into its project management framework for a three-year infrastructure project. The Project Manager is currently drafting the Team Management Plan and needs to address high turnover rates observed in previous high-pressure phases. Which approach best demonstrates the effective application of Managing Project Team principles when incorporating health and wellness into the project lifecycle?
Correct
Correct: Integrating wellness objectives into the team charter and performance assessments is the most effective approach because it embeds health and wellness into the project’s core culture and management processes. By including these elements in the team charter, the Project Manager establishes shared values and expectations. Monitoring burnout through performance assessments allows for proactive management of team health, which is a key component of the Managing Project Team process, leading to improved productivity and lower turnover.
Incorrect: Restricting initiatives to the initiation phase is incorrect because team development and management are ongoing processes that require attention throughout the project lifecycle. Implementing a bonus tied only to safety milestones focuses on outcomes rather than the ongoing well-being of the staff and may lead to underreporting of issues. Delegating all monitoring to human resources is a failure of the Project Manager’s responsibility to manage their team directly; while HR provides support, the PM must be actively involved in the team’s health and dynamics to ensure project success.
Takeaway: Effective team management requires integrating health and wellness into the project’s foundational documents and ongoing performance management to ensure long-term team stability and project success.
Incorrect
Correct: Integrating wellness objectives into the team charter and performance assessments is the most effective approach because it embeds health and wellness into the project’s core culture and management processes. By including these elements in the team charter, the Project Manager establishes shared values and expectations. Monitoring burnout through performance assessments allows for proactive management of team health, which is a key component of the Managing Project Team process, leading to improved productivity and lower turnover.
Incorrect: Restricting initiatives to the initiation phase is incorrect because team development and management are ongoing processes that require attention throughout the project lifecycle. Implementing a bonus tied only to safety milestones focuses on outcomes rather than the ongoing well-being of the staff and may lead to underreporting of issues. Delegating all monitoring to human resources is a failure of the Project Manager’s responsibility to manage their team directly; while HR provides support, the PM must be actively involved in the team’s health and dynamics to ensure project success.
Takeaway: Effective team management requires integrating health and wellness into the project’s foundational documents and ongoing performance management to ensure long-term team stability and project success.
-
Question 8 of 8
8. Question
Working as the information security manager for an audit firm, you encounter a situation involving Dispute Resolution Processes during complaints handling. Upon examining a control testing result, you discover that a project manager for a large-scale infrastructure build-out bypassed the mandatory 30-day “meet and confer” period specified in the contract after a $75,000 claim was rejected. Instead, the manager immediately filed for formal arbitration. Which of the following represents the primary risk to the organization regarding this procedural bypass?
Correct
Correct: In construction management and project law, dispute resolution clauses often contain ‘conditions precedent.’ These are mandatory steps, such as a ‘meet and confer’ period or mediation, that must be completed before a party has the legal right to pursue arbitration or litigation. If these steps are bypassed, the arbitrator or court may stay the proceedings or dismiss the claim entirely until the contractual requirements are met. This results in wasted legal fees, administrative overhead, and a significant delay in resolving the actual dispute.
Incorrect: While a dispute might impact the project schedule, it does not automatically render the entire Work Breakdown Structure (WBS) obsolete; the WBS is a tool for scope management, not a legal document tied to specific dispute filings. The project charter is an internal document that authorizes the project and the manager’s use of resources; it is not nullified by a breach of a contract’s dispute resolution clause. Suspending the communication management plan is not a standard consequence of a dispute; in fact, maintaining communication is critical during a dispute to prevent further escalation.
Takeaway: Adhering to contractually mandated dispute resolution steps is a critical risk management function to ensure that claims are not dismissed for failing to meet conditions precedent.
Incorrect
Correct: In construction management and project law, dispute resolution clauses often contain ‘conditions precedent.’ These are mandatory steps, such as a ‘meet and confer’ period or mediation, that must be completed before a party has the legal right to pursue arbitration or litigation. If these steps are bypassed, the arbitrator or court may stay the proceedings or dismiss the claim entirely until the contractual requirements are met. This results in wasted legal fees, administrative overhead, and a significant delay in resolving the actual dispute.
Incorrect: While a dispute might impact the project schedule, it does not automatically render the entire Work Breakdown Structure (WBS) obsolete; the WBS is a tool for scope management, not a legal document tied to specific dispute filings. The project charter is an internal document that authorizes the project and the manager’s use of resources; it is not nullified by a breach of a contract’s dispute resolution clause. Suspending the communication management plan is not a standard consequence of a dispute; in fact, maintaining communication is critical during a dispute to prevent further escalation.
Takeaway: Adhering to contractually mandated dispute resolution steps is a critical risk management function to ensure that claims are not dismissed for failing to meet conditions precedent.