Quiz-summary
0 of 10 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
Information
Premium Practice Questions
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 10 questions answered correctly
Your time:
Time has elapsed
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Answered
- Review
-
Question 1 of 10
1. Question
When a problem arises concerning LEED v4.1 rating levels (Certified, Silver, Gold, Platinum), what should be the immediate priority? A project team is pursuing LEED Gold certification for a new office development. During the final stages of construction, a documentation audit reveals that a specific material substitution has resulted in the loss of several points in the Materials and Resources category, potentially dropping the project’s total score below the 60-point threshold. Before attempting to identify new credits to regain the Gold status, what must the project team verify to ensure the project remains eligible for any level of certification?
Correct
Correct: In the LEED v4.1 rating system, prerequisites and Minimum Program Requirements (MPRs) are mandatory and do not earn points. Regardless of whether a project is aiming for Certified, Silver, Gold, or Platinum, failure to meet even one prerequisite or MPR disqualifies the project from certification entirely. When a project’s point total is threatened, the immediate priority is to ensure that the fundamental requirements for certification are still met, as points are irrelevant if the project is no longer eligible.
Incorrect: Submitting a CIR is a process for seeking technical guidance on specific credit requirements but does not bypass the necessity of meeting prerequisites. Purchasing RECs may provide points in the Energy and Atmosphere category, but it is a secondary strategy that does not address the primary risk of failing a prerequisite. Re-evaluating the project boundary to exclude non-compliant areas is generally not permitted under LEED Minimum Program Requirements, which require a consistent and reasonable boundary.
Takeaway: Regardless of the target certification level, meeting all prerequisites and Minimum Program Requirements is the mandatory foundation for any LEED project.
Incorrect
Correct: In the LEED v4.1 rating system, prerequisites and Minimum Program Requirements (MPRs) are mandatory and do not earn points. Regardless of whether a project is aiming for Certified, Silver, Gold, or Platinum, failure to meet even one prerequisite or MPR disqualifies the project from certification entirely. When a project’s point total is threatened, the immediate priority is to ensure that the fundamental requirements for certification are still met, as points are irrelevant if the project is no longer eligible.
Incorrect: Submitting a CIR is a process for seeking technical guidance on specific credit requirements but does not bypass the necessity of meeting prerequisites. Purchasing RECs may provide points in the Energy and Atmosphere category, but it is a secondary strategy that does not address the primary risk of failing a prerequisite. Re-evaluating the project boundary to exclude non-compliant areas is generally not permitted under LEED Minimum Program Requirements, which require a consistent and reasonable boundary.
Takeaway: Regardless of the target certification level, meeting all prerequisites and Minimum Program Requirements is the mandatory foundation for any LEED project.
-
Question 2 of 10
2. Question
As the privacy officer at a private bank, you are reviewing Water-efficient technologies for urban agriculture and green spaces during record-keeping when a control testing result arrives on your desk. It reveals that the bank’s rooftop urban farm is currently consuming potable water at a rate 40% higher than the design baseline, jeopardizing the project’s LEED Outdoor Water Use Reduction credit. To mitigate this operational risk and ensure the facility meets LEED v4.1 requirements for sustainable water management, which of the following strategies should be implemented?
Correct
Correct: In the LEED rating system, the Outdoor Water Use Reduction credit focuses on reducing the demand for potable water. Weather-based irrigation controllers (WBIC) use local weather data and real-time evapotranspiration rates to adjust irrigation schedules, preventing overwatering. Furthermore, substituting potable water with non-potable sources, such as captured rainwater, is a primary strategy for achieving significant reductions in municipal water consumption for landscaping and urban agriculture.
Incorrect: Manual watering is inefficient and lacks the precision of automated, data-driven systems. Overhead sprinklers are generally less efficient than drip irrigation because they lose more water to evaporation and wind drift. Synthetic fertilizers do not address water efficiency and can lead to environmental degradation through nutrient runoff, which contradicts the foundational principles of green building and the triple bottom line.
Takeaway: Achieving LEED outdoor water reduction requires a combination of smart irrigation technology and the use of non-potable water sources to minimize reliance on municipal systems.
Incorrect
Correct: In the LEED rating system, the Outdoor Water Use Reduction credit focuses on reducing the demand for potable water. Weather-based irrigation controllers (WBIC) use local weather data and real-time evapotranspiration rates to adjust irrigation schedules, preventing overwatering. Furthermore, substituting potable water with non-potable sources, such as captured rainwater, is a primary strategy for achieving significant reductions in municipal water consumption for landscaping and urban agriculture.
Incorrect: Manual watering is inefficient and lacks the precision of automated, data-driven systems. Overhead sprinklers are generally less efficient than drip irrigation because they lose more water to evaporation and wind drift. Synthetic fertilizers do not address water efficiency and can lead to environmental degradation through nutrient runoff, which contradicts the foundational principles of green building and the triple bottom line.
Takeaway: Achieving LEED outdoor water reduction requires a combination of smart irrigation technology and the use of non-potable water sources to minimize reliance on municipal systems.
-
Question 3 of 10
3. Question
During your tenure as operations manager at an insurer, a matter arises concerning Documentation requirements for specific LEED credits during client suitability. The a control testing result suggests that the documentation provided for a client’s LEED v4.1 Building Design and Construction project is insufficient for the ‘Surrounding Density and Diverse Uses’ credit. While the client provided a list of nearby businesses, the submission lacks the mandatory spatial evidence required for USGBC review. Which of the following must be provided to meet the documentation requirements for this credit?
Correct
Correct: For the ‘Surrounding Density and Diverse Uses’ credit under LEED v4.1, the project team must provide an area map that clearly identifies the project building and the 1/4-mile (400-meter) walking distance radius. This map serves as the primary evidence that the diverse uses are within the required pedestrian distance, which is a core requirement for the Location and Transportation category. LEED Online requires this visual verification to ensure that the amenities are accessible via safe walking paths rather than just being nearby in a straight-line distance.
Incorrect: A certified land survey for building square footage is more relevant to the ‘Surrounding Density’ portion of the credit rather than ‘Diverse Uses,’ and the radius for density is typically 1/4 mile, not 1/2 mile. Signed statements from local departments are not accepted as a substitute for the required spatial maps and walking distance calculations in the LEED certification process. While pedestrian safety is a goal of LEED, photographs of intersections do not provide the necessary verification of the proximity and variety of diverse uses required for credit achievement.
Takeaway: LEED documentation for location-based credits requires specific spatial maps that demonstrate walking distances to amenities rather than simple lists or straight-line measurements.
Incorrect
Correct: For the ‘Surrounding Density and Diverse Uses’ credit under LEED v4.1, the project team must provide an area map that clearly identifies the project building and the 1/4-mile (400-meter) walking distance radius. This map serves as the primary evidence that the diverse uses are within the required pedestrian distance, which is a core requirement for the Location and Transportation category. LEED Online requires this visual verification to ensure that the amenities are accessible via safe walking paths rather than just being nearby in a straight-line distance.
Incorrect: A certified land survey for building square footage is more relevant to the ‘Surrounding Density’ portion of the credit rather than ‘Diverse Uses,’ and the radius for density is typically 1/4 mile, not 1/2 mile. Signed statements from local departments are not accepted as a substitute for the required spatial maps and walking distance calculations in the LEED certification process. While pedestrian safety is a goal of LEED, photographs of intersections do not provide the necessary verification of the proximity and variety of diverse uses required for credit achievement.
Takeaway: LEED documentation for location-based credits requires specific spatial maps that demonstrate walking distances to amenities rather than simple lists or straight-line measurements.
-
Question 4 of 10
4. Question
In managing Local economic development initiatives, which control most effectively reduces the key risk of economic leakage and ensures the project supports the Triple Bottom Line? A project team is planning a new commercial development in a qualifying census tract and aims to maximize the social and economic benefits to the immediate neighborhood.
Correct
Correct: In the context of LEED and the Triple Bottom Line, local economic development is best supported by keeping financial resources within the community. By implementing policies that prioritize local hiring and sourcing, the project directly addresses the ‘Social’ and ‘Economic’ pillars, reducing the risk that the investment benefits only outside entities (economic leakage). This approach fosters community resilience and supports the local tax base.
Incorrect: Sourcing from global manufacturers may improve energy efficiency but does not specifically address local economic development. Purchasing national RECs helps mitigate climate change globally but provides no direct economic stimulus to the local project site. Increasing parking capacity often contradicts LEED goals regarding density and alternative transportation, and focusing on outside commuters does not necessarily strengthen the local neighborhood economy.
Takeaway: Effective local economic development in green building requires intentional strategies to integrate the project into the local economy through community-based hiring and procurement practices.
Incorrect
Correct: In the context of LEED and the Triple Bottom Line, local economic development is best supported by keeping financial resources within the community. By implementing policies that prioritize local hiring and sourcing, the project directly addresses the ‘Social’ and ‘Economic’ pillars, reducing the risk that the investment benefits only outside entities (economic leakage). This approach fosters community resilience and supports the local tax base.
Incorrect: Sourcing from global manufacturers may improve energy efficiency but does not specifically address local economic development. Purchasing national RECs helps mitigate climate change globally but provides no direct economic stimulus to the local project site. Increasing parking capacity often contradicts LEED goals regarding density and alternative transportation, and focusing on outside commuters does not necessarily strengthen the local neighborhood economy.
Takeaway: Effective local economic development in green building requires intentional strategies to integrate the project into the local economy through community-based hiring and procurement practices.
-
Question 5 of 10
5. Question
Following an on-site examination at a broker-dealer, regulators raised concerns about Life Cycle Assessment (LCA) tools and methodologies in the context of risk appetite review. Their preliminary finding is that the firm’s sustainability reporting for its new headquarters lacked a comprehensive analysis of environmental stressors. The project team is tasked with performing a whole-building LCA to achieve LEED certification. Which of the following best describes the scope of a cradle-to-grave Life Cycle Assessment as defined by LEED standards?
Correct
Correct: A Life Cycle Assessment (LCA) is a comprehensive ‘cradle-to-grave’ or ‘cradle-to-cradle’ evaluation of the environmental footprint of a product or building. It examines all stages of a product’s life, including raw material extraction, manufacturing, transportation, use, and end-of-life (demolition, disposal, or recycling). In LEED, this methodology is used to quantify impacts such as global warming potential and ozone depletion.
Incorrect: The financial analysis of initial and long-term costs describes Life Cycle Costing (LCC), which is distinct from the environmental focus of an LCA. Verifying sustainable harvesting practices refers to specific material certifications (like FSC for wood) rather than a whole-building assessment. Measuring water consumption reduction is a requirement of the Water Efficiency category, not the Material and Resources LCA process.
Takeaway: A Life Cycle Assessment (LCA) provides a holistic view of environmental impacts across all stages of a building’s or material’s life cycle, from extraction to disposal.
Incorrect
Correct: A Life Cycle Assessment (LCA) is a comprehensive ‘cradle-to-grave’ or ‘cradle-to-cradle’ evaluation of the environmental footprint of a product or building. It examines all stages of a product’s life, including raw material extraction, manufacturing, transportation, use, and end-of-life (demolition, disposal, or recycling). In LEED, this methodology is used to quantify impacts such as global warming potential and ozone depletion.
Incorrect: The financial analysis of initial and long-term costs describes Life Cycle Costing (LCC), which is distinct from the environmental focus of an LCA. Verifying sustainable harvesting practices refers to specific material certifications (like FSC for wood) rather than a whole-building assessment. Measuring water consumption reduction is a requirement of the Water Efficiency category, not the Material and Resources LCA process.
Takeaway: A Life Cycle Assessment (LCA) provides a holistic view of environmental impacts across all stages of a building’s or material’s life cycle, from extraction to disposal.
-
Question 6 of 10
6. Question
The board of directors at a mid-sized retail bank has asked for a recommendation regarding Biophilic design elements and their implementation as part of record-keeping. The background paper states that while the bank is digitizing its archives, the physical workspace for the administrative staff must be redesigned to support long-term health and productivity over a 24-month operational cycle. The project team is tasked with selecting features that foster a connection between the staff and the natural environment. Which of the following strategies most effectively implements biophilic design principles?
Correct
Correct: Biophilic design is centered on the inherent human need to connect with nature. Strategies such as circadian lighting, which mimics the sun’s natural cycle, and providing views of greenery are direct applications of biophilic principles. These elements are specifically intended to reduce stress, improve cognitive function, and enhance the overall well-being of building occupants.
Incorrect: Increasing ventilation rates focuses on mechanical indoor environmental quality (IEQ) and air purity rather than nature-based design. Using low-VOC materials and recycled content addresses material safety and resource conservation within the Materials and Resources (MR) or IEQ categories. Digital record-keeping is a waste reduction and resource efficiency strategy that does not involve biophilic elements or the human-nature connection.
Takeaway: Biophilic design prioritizes the integration of natural patterns, light, and views to enhance the human experience and well-being within the built environment.
Incorrect
Correct: Biophilic design is centered on the inherent human need to connect with nature. Strategies such as circadian lighting, which mimics the sun’s natural cycle, and providing views of greenery are direct applications of biophilic principles. These elements are specifically intended to reduce stress, improve cognitive function, and enhance the overall well-being of building occupants.
Incorrect: Increasing ventilation rates focuses on mechanical indoor environmental quality (IEQ) and air purity rather than nature-based design. Using low-VOC materials and recycled content addresses material safety and resource conservation within the Materials and Resources (MR) or IEQ categories. Digital record-keeping is a waste reduction and resource efficiency strategy that does not involve biophilic elements or the human-nature connection.
Takeaway: Biophilic design prioritizes the integration of natural patterns, light, and views to enhance the human experience and well-being within the built environment.
-
Question 7 of 10
7. Question
During a committee meeting at a private bank, a question arises about Regional materials as part of data protection. The discussion reveals that the internal audit team is reviewing the sustainability documentation for a new corporate headquarters to ensure compliance with LEED v4.1 standards. A specific concern is raised regarding the ‘Location Valuation Factor’ and how it applies to the cost calculations for the Building Product Disclosure and Optimization credits. To ensure the audit is accurate, the team must identify the specific distance threshold required for a product to be valued at 200% of its cost.
Correct
Correct: In LEED v4 and v4.1, the ‘Location Valuation Factor’ is a multiplier that encourages the use of local materials. For a material to qualify for this 200% valuation (double its actual cost) in the context of Building Product Disclosure and Optimization (BPDO) credits, it must be extracted, manufactured, and purchased within a 100-mile (160 km) radius of the project site.
Incorrect: The 500-mile radius was the standard used in older versions of LEED (such as LEED 2009) but was significantly reduced in LEED v4 to promote more localized sourcing. Sourcing from within the same state is not a LEED requirement, as the system uses a strict radius that ignores political boundaries. The 250-mile threshold is not a recognized distance for the location valuation factor in the current LEED v4.1 rating system.
Takeaway: To qualify for the LEED v4.1 location valuation factor, a material must meet the extraction, manufacturing, and purchase requirements within a 100-mile (160 km) radius of the project.
Incorrect
Correct: In LEED v4 and v4.1, the ‘Location Valuation Factor’ is a multiplier that encourages the use of local materials. For a material to qualify for this 200% valuation (double its actual cost) in the context of Building Product Disclosure and Optimization (BPDO) credits, it must be extracted, manufactured, and purchased within a 100-mile (160 km) radius of the project site.
Incorrect: The 500-mile radius was the standard used in older versions of LEED (such as LEED 2009) but was significantly reduced in LEED v4 to promote more localized sourcing. Sourcing from within the same state is not a LEED requirement, as the system uses a strict radius that ignores political boundaries. The 250-mile threshold is not a recognized distance for the location valuation factor in the current LEED v4.1 rating system.
Takeaway: To qualify for the LEED v4.1 location valuation factor, a material must meet the extraction, manufacturing, and purchase requirements within a 100-mile (160 km) radius of the project.
-
Question 8 of 10
8. Question
How can the inherent risks in Sustainable building materials and their properties be most effectively addressed? A project team is seeking to reduce the environmental footprint of a new construction project by selecting materials with the lowest life-cycle impact. To make an informed decision that considers the full range of environmental consequences from raw material extraction through end-of-life, which documentation should the team prioritize during the material selection process?
Correct
Correct: Environmental Product Declarations (EPDs) are standardized, third-party verified documents based on Life Cycle Assessment (LCA) data. They provide a comprehensive look at a product’s environmental impact across multiple categories, such as global warming potential, ozone depletion, and resource depletion, throughout its entire life cycle (cradle-to-grave). This allows project teams to make holistic decisions based on environmental performance.
Incorrect: Selecting materials based on pre-consumer recycled content only addresses one specific attribute of a material and does not provide a full life-cycle perspective. Health Product Declarations (HPDs) are designed to disclose chemical ingredients and associated human health hazards, not environmental impacts like carbon footprint or energy intensity. Focusing on salvageability addresses the end-of-life phase but fails to account for the significant impacts occurring during raw material extraction and manufacturing.
Takeaway: Environmental Product Declarations (EPDs) are the primary tool in LEED for evaluating the comprehensive, life-cycle environmental impacts of building materials.
Incorrect
Correct: Environmental Product Declarations (EPDs) are standardized, third-party verified documents based on Life Cycle Assessment (LCA) data. They provide a comprehensive look at a product’s environmental impact across multiple categories, such as global warming potential, ozone depletion, and resource depletion, throughout its entire life cycle (cradle-to-grave). This allows project teams to make holistic decisions based on environmental performance.
Incorrect: Selecting materials based on pre-consumer recycled content only addresses one specific attribute of a material and does not provide a full life-cycle perspective. Health Product Declarations (HPDs) are designed to disclose chemical ingredients and associated human health hazards, not environmental impacts like carbon footprint or energy intensity. Focusing on salvageability addresses the end-of-life phase but fails to account for the significant impacts occurring during raw material extraction and manufacturing.
Takeaway: Environmental Product Declarations (EPDs) are the primary tool in LEED for evaluating the comprehensive, life-cycle environmental impacts of building materials.
-
Question 9 of 10
9. Question
Senior management at a mid-sized retail bank requests your input on Photographic evidence as part of outsourcing. Their briefing note explains that the bank is concerned about the integrity of the LEED certification process for its new regional office. As an internal auditor reviewing the project’s documentation controls, you are evaluating the requirement for photographic evidence during the construction phase, specifically regarding the protection of installed ductwork and on-site materials to ensure indoor air quality. Which of the following best describes the significance of photographic evidence within the LEED documentation and review framework?
Correct
Correct: Photographic evidence is a standard documentation requirement for various LEED credits, such as Construction Indoor Air Quality Management or Construction Activity Pollution Prevention. It serves as visual proof for the Green Business Certification Inc. (GBCI) reviewers that the strategies and plans described in the application were actually implemented on the job site, bridging the gap between theoretical plans and physical execution.
Incorrect: Photographic evidence does not provide a legally binding guarantee of future performance, as building operations depend on many variables beyond initial construction. It is not a universal requirement for every credit; many credits rely solely on calculations, maps, or receipts. Furthermore, GBCI typically performs desk audits of documentation submitted via LEED Online; on-site verification visits are not mandatory for all LEED projects and are relatively rare.
Takeaway: Photographic evidence is a critical verification tool in LEED documentation used to confirm the physical implementation of construction-phase sustainability strategies.
Incorrect
Correct: Photographic evidence is a standard documentation requirement for various LEED credits, such as Construction Indoor Air Quality Management or Construction Activity Pollution Prevention. It serves as visual proof for the Green Business Certification Inc. (GBCI) reviewers that the strategies and plans described in the application were actually implemented on the job site, bridging the gap between theoretical plans and physical execution.
Incorrect: Photographic evidence does not provide a legally binding guarantee of future performance, as building operations depend on many variables beyond initial construction. It is not a universal requirement for every credit; many credits rely solely on calculations, maps, or receipts. Furthermore, GBCI typically performs desk audits of documentation submitted via LEED Online; on-site verification visits are not mandatory for all LEED projects and are relatively rare.
Takeaway: Photographic evidence is a critical verification tool in LEED documentation used to confirm the physical implementation of construction-phase sustainability strategies.
-
Question 10 of 10
10. Question
In assessing competing strategies for Smart water meters, what distinguishes the best option? A project team for a new commercial office building is evaluating how to implement a metering system that supports both LEED v4.1 Water Efficiency requirements and long-term operational sustainability.
Correct
Correct: The best strategy for smart water metering involves submetering specific high-use subsystems (such as cooling towers, irrigation, and domestic hot water) and integrating that data into a centralized Building Automation System (BAS). This allows for real-time monitoring, which is essential for identifying leaks immediately and benchmarking the performance of individual systems against efficiency goals, directly supporting LEED’s emphasis on ongoing performance and data-driven management.
Incorrect: Focusing on high-efficiency fixtures is a water reduction strategy rather than a metering strategy. Manual-read meters do not provide the real-time data or automation necessary for modern smart building management and are prone to human error. Relying solely on aggregate municipal data lacks the granularity required to identify specific system failures or to meet LEED requirements for submetering individual high-intensity water uses.
Takeaway: Effective smart water metering requires granular submetering integrated into a centralized system to enable real-time monitoring and proactive maintenance.
Incorrect
Correct: The best strategy for smart water metering involves submetering specific high-use subsystems (such as cooling towers, irrigation, and domestic hot water) and integrating that data into a centralized Building Automation System (BAS). This allows for real-time monitoring, which is essential for identifying leaks immediately and benchmarking the performance of individual systems against efficiency goals, directly supporting LEED’s emphasis on ongoing performance and data-driven management.
Incorrect: Focusing on high-efficiency fixtures is a water reduction strategy rather than a metering strategy. Manual-read meters do not provide the real-time data or automation necessary for modern smart building management and are prone to human error. Relying solely on aggregate municipal data lacks the granularity required to identify specific system failures or to meet LEED requirements for submetering individual high-intensity water uses.
Takeaway: Effective smart water metering requires granular submetering integrated into a centralized system to enable real-time monitoring and proactive maintenance.