Quiz-summary
0 of 10 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
Information
Premium Practice Questions
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 10 questions answered correctly
Your time:
Time has elapsed
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Answered
- Review
-
Question 1 of 10
1. Question
The supervisory authority has issued an inquiry to an insurer concerning Archiving Project Information in the context of gifts and entertainment. The letter states that during a recent audit of the Corporate Compliance Project, several records regarding the approval of vendor-sponsored events were missing from the official project repository. The project manager is now preparing the final project closure report and must ensure that all remaining artifacts, including the gift registry and the rationale for entertainment exceptions, are properly preserved. Given that the insurer is subject to a 7-year regulatory retention period for compliance-related data, which action should the project manager take to finalize the archiving process?
Correct
Correct: In project management, archiving involves the systematic collection, indexing, and storage of all relevant project information to meet both organizational and regulatory requirements. For an insurer facing a supervisory inquiry, it is critical that the audit trail—including decision logs and rationale for exceptions—is preserved in a formal corporate archive. This ensures that the information is retrievable for future audits and complies with the specified 7-year retention period.
Incorrect: Purging interim drafts and informal approvals is incorrect because these often contain the decision-making logic required for regulatory audits. Storing physical registries in a local office file rather than a centralized archive creates a risk of data loss and fragmentation, making it difficult to respond to future inquiries. Simply setting a shared drive to read-only is not a substitute for formal archiving, as shared drives are often not managed under long-term retention policies and restricting access only to the original team may prevent authorized auditors from accessing the data.
Takeaway: Effective project archiving requires the centralized, indexed preservation of all project artifacts and decision logs to satisfy long-term regulatory and organizational audit requirements.
Incorrect
Correct: In project management, archiving involves the systematic collection, indexing, and storage of all relevant project information to meet both organizational and regulatory requirements. For an insurer facing a supervisory inquiry, it is critical that the audit trail—including decision logs and rationale for exceptions—is preserved in a formal corporate archive. This ensures that the information is retrievable for future audits and complies with the specified 7-year retention period.
Incorrect: Purging interim drafts and informal approvals is incorrect because these often contain the decision-making logic required for regulatory audits. Storing physical registries in a local office file rather than a centralized archive creates a risk of data loss and fragmentation, making it difficult to respond to future inquiries. Simply setting a shared drive to read-only is not a substitute for formal archiving, as shared drives are often not managed under long-term retention policies and restricting access only to the original team may prevent authorized auditors from accessing the data.
Takeaway: Effective project archiving requires the centralized, indexed preservation of all project artifacts and decision logs to satisfy long-term regulatory and organizational audit requirements.
-
Question 2 of 10
2. Question
Your team is drafting a policy on Contract Closeout as part of transaction monitoring for a mid-sized retail bank. A key unresolved point is the specific sequence of administrative and legal actions required when a vendor has completed the technical implementation of a new anti-money laundering (AML) module. The project manager needs to ensure that the bank’s interests are protected before the final 15% retention payment is released. Which action should be prioritized to ensure the contract is formally closed according to standard project management practices?
Correct
Correct: In project procurement management, contract closeout involves the formal verification that all work and deliverables are acceptable. This process includes administrative activities such as updating records to reflect final results and notifying the vendor in writing that the contract is complete. This formal notice is a critical legal step before final payments are settled.
Incorrect: Archiving documentation and conducting team reviews are components of administrative project closure, but they do not specifically address the legal and procurement-specific requirements of closing a contract with an external vendor. Releasing payment immediately after UAT is premature, as it bypasses the formal acceptance and administrative closure steps. Updating the lessons learned register is a valuable organizational process asset update but does not satisfy the requirement for formal contract closure.
Takeaway: Contract closeout requires formal deliverable acceptance and written notification to the vendor to legally conclude the procurement agreement.
Incorrect
Correct: In project procurement management, contract closeout involves the formal verification that all work and deliverables are acceptable. This process includes administrative activities such as updating records to reflect final results and notifying the vendor in writing that the contract is complete. This formal notice is a critical legal step before final payments are settled.
Incorrect: Archiving documentation and conducting team reviews are components of administrative project closure, but they do not specifically address the legal and procurement-specific requirements of closing a contract with an external vendor. Releasing payment immediately after UAT is premature, as it bypasses the formal acceptance and administrative closure steps. Updating the lessons learned register is a valuable organizational process asset update but does not satisfy the requirement for formal contract closure.
Takeaway: Contract closeout requires formal deliverable acceptance and written notification to the vendor to legally conclude the procurement agreement.
-
Question 3 of 10
3. Question
As the client onboarding lead at a fund administrator, you are reviewing Power/Interest Grid during third-party risk when a policy exception request arrives on your desk. It reveals that a senior managing director from the investment division, who has significant influence over annual budget allocations but rarely interacts with the daily onboarding workflow, is demanding an expedited bypass of the standard 30-day vendor cooling-off period. You need to determine the most appropriate stakeholder engagement strategy for this managing director to ensure project alignment and minimize potential friction.
Correct
Correct: According to the Power/Interest Grid, stakeholders with high power but low interest should be ‘Kept Satisfied.’ In this scenario, the managing director has high power (influence over budgets) but low interest (rarely interacts with the workflow). The project manager should meet their needs and keep them satisfied with high-level information to ensure they do not use their influence to negatively impact the project, without overwhelming them with unnecessary details.
Incorrect: Managing a stakeholder closely is the strategy for those with both high power and high interest, which would be an inefficient use of time for a low-interest executive. Monitoring with minimal effort is reserved for stakeholders with both low power and low interest. Keeping a stakeholder informed with detailed technical data is the strategy for those with low power but high interest, as it provides the detail they desire without requiring high-level satisfaction management.
Takeaway: Stakeholders with high power and low interest must be kept satisfied through strategic, high-level communication to prevent them from exercising their influence against project objectives.
Incorrect
Correct: According to the Power/Interest Grid, stakeholders with high power but low interest should be ‘Kept Satisfied.’ In this scenario, the managing director has high power (influence over budgets) but low interest (rarely interacts with the workflow). The project manager should meet their needs and keep them satisfied with high-level information to ensure they do not use their influence to negatively impact the project, without overwhelming them with unnecessary details.
Incorrect: Managing a stakeholder closely is the strategy for those with both high power and high interest, which would be an inefficient use of time for a low-interest executive. Monitoring with minimal effort is reserved for stakeholders with both low power and low interest. Keeping a stakeholder informed with detailed technical data is the strategy for those with low power but high interest, as it provides the detail they desire without requiring high-level satisfaction management.
Takeaway: Stakeholders with high power and low interest must be kept satisfied through strategic, high-level communication to prevent them from exercising their influence against project objectives.
-
Question 4 of 10
4. Question
Working as the client onboarding lead for a credit union, you encounter a situation involving Quality Performance during regulatory inspection. Upon examining a suspicious activity escalation, you discover that the automated KYC verification system has a 15% failure rate in identifying high-risk jurisdictions, which significantly exceeds the 5% threshold established in the Quality Management Plan. The regulator indicates that the current quality metrics are insufficient for ensuring compliance with anti-money laundering standards. What is the most appropriate action to ensure the project’s quality performance meets these requirements?
Correct
Correct: When quality performance data indicates that established metrics are not being met or are insufficient for regulatory compliance, the project manager must perform a root cause analysis to understand the gap. Following this, any changes to the Quality Management Plan or the metrics themselves must be processed through the formal Perform Integrated Change Control process to ensure the project remains aligned with stakeholder expectations and regulatory requirements.
Incorrect: Implementing 100% manual inspection is a reactive measure that focuses on quality control (finding defects) rather than quality management (preventing defects) and does not address the underlying metric insufficiency. Updating the plan to accept a higher failure rate is a violation of quality standards and regulatory compliance. Increasing audits of coding standards focuses on a specific technical aspect that may not be the root cause of the metric failure and does not address the need to update the overall quality framework.
Takeaway: Quality performance issues require a systematic approach of identifying root causes and updating the quality management framework through formal change control to maintain regulatory alignment.
Incorrect
Correct: When quality performance data indicates that established metrics are not being met or are insufficient for regulatory compliance, the project manager must perform a root cause analysis to understand the gap. Following this, any changes to the Quality Management Plan or the metrics themselves must be processed through the formal Perform Integrated Change Control process to ensure the project remains aligned with stakeholder expectations and regulatory requirements.
Incorrect: Implementing 100% manual inspection is a reactive measure that focuses on quality control (finding defects) rather than quality management (preventing defects) and does not address the underlying metric insufficiency. Updating the plan to accept a higher failure rate is a violation of quality standards and regulatory compliance. Increasing audits of coding standards focuses on a specific technical aspect that may not be the root cause of the metric failure and does not address the need to update the overall quality framework.
Takeaway: Quality performance issues require a systematic approach of identifying root causes and updating the quality management framework through formal change control to maintain regulatory alignment.
-
Question 5 of 10
5. Question
How do different methodologies for Control Schedule compare in terms of effectiveness? A project manager is leading a large-scale software integration project that utilizes a hybrid approach. During the most recent performance review, the project manager observes that while the critical path activities are currently on track, several non-critical activities are slipping significantly. This slippage is beginning to consume the available float and threatens to create resource conflicts for upcoming critical tasks. Which approach to schedule control would be most effective in maintaining the project’s overall health while minimizing disruption to the baseline?
Correct
Correct: Trend analysis is a powerful tool in the Control Schedule process because it examines project performance over time to determine if performance is improving or deteriorating. By identifying a downward trend in non-critical activities early, the project manager can use resource optimization (such as resource leveling or smoothing) to prevent these delays from causing resource scarcity for critical path activities. This proactive approach maintains the integrity of the schedule baseline while managing risks before they manifest as critical delays.
Incorrect: Re-baselining is a reactive measure that should only be used when the project scope has changed significantly or the original baseline is no longer achievable; using it for minor slippages hides performance issues rather than solving them. Fast-tracking non-critical activities is often counterproductive as it increases risk and complexity without necessarily shortening the project duration, which is determined by the critical path. Focusing only on the critical path is a common mistake; non-critical activities must be monitored because if their float is entirely consumed, they become part of a new critical path, potentially delaying the entire project.
Takeaway: Effective schedule control involves proactive trend analysis and resource management to ensure that slippage in non-critical activities does not eventually compromise the critical path or resource availability.
Incorrect
Correct: Trend analysis is a powerful tool in the Control Schedule process because it examines project performance over time to determine if performance is improving or deteriorating. By identifying a downward trend in non-critical activities early, the project manager can use resource optimization (such as resource leveling or smoothing) to prevent these delays from causing resource scarcity for critical path activities. This proactive approach maintains the integrity of the schedule baseline while managing risks before they manifest as critical delays.
Incorrect: Re-baselining is a reactive measure that should only be used when the project scope has changed significantly or the original baseline is no longer achievable; using it for minor slippages hides performance issues rather than solving them. Fast-tracking non-critical activities is often counterproductive as it increases risk and complexity without necessarily shortening the project duration, which is determined by the critical path. Focusing only on the critical path is a common mistake; non-critical activities must be monitored because if their float is entirely consumed, they become part of a new critical path, potentially delaying the entire project.
Takeaway: Effective schedule control involves proactive trend analysis and resource management to ensure that slippage in non-critical activities does not eventually compromise the critical path or resource availability.
-
Question 6 of 10
6. Question
The compliance framework at a credit union is being updated to address Estimate Activity Durations as part of control testing. A challenge arises because the project team, tasked with a high-priority 18-month digital transformation, is reporting significant variance in duration estimates for core banking integration tasks. The Project Management Office (PMO) notes that while the current team is experienced, they lack a standardized approach for leveraging past performance data. To ensure the schedule remains realistic and defensible for regulatory audit purposes, which approach should the project manager prioritize?
Correct
Correct: Analogous estimating is a technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project. In this scenario, using the credit union’s own historical data from a previous infrastructure upgrade provides a reliable, top-down estimate that reflects the organization’s specific environment, culture, and technical capabilities, which is essential for creating a defensible schedule for audit purposes.
Incorrect: Applying a flat contingency reserve is a risk management strategy rather than an estimation technique and does not improve the accuracy of the underlying duration estimates. Using aggressive or optimistic estimates is a poor practice that ignores project risks and leads to unrealistic schedules. Parametric estimating based on generic industry standards often fails to account for internal organizational complexities, such as specific compliance workflows or legacy system constraints unique to the credit union’s environment.
Takeaway: Leveraging historical organizational data through analogous estimating provides a realistic and defensible foundation for project schedules when detailed activity data is inconsistent or limited in the early planning stages of a project phase.
Incorrect
Correct: Analogous estimating is a technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project. In this scenario, using the credit union’s own historical data from a previous infrastructure upgrade provides a reliable, top-down estimate that reflects the organization’s specific environment, culture, and technical capabilities, which is essential for creating a defensible schedule for audit purposes.
Incorrect: Applying a flat contingency reserve is a risk management strategy rather than an estimation technique and does not improve the accuracy of the underlying duration estimates. Using aggressive or optimistic estimates is a poor practice that ignores project risks and leads to unrealistic schedules. Parametric estimating based on generic industry standards often fails to account for internal organizational complexities, such as specific compliance workflows or legacy system constraints unique to the credit union’s environment.
Takeaway: Leveraging historical organizational data through analogous estimating provides a realistic and defensible foundation for project schedules when detailed activity data is inconsistent or limited in the early planning stages of a project phase.
-
Question 7 of 10
7. Question
Following an on-site examination at a listed company, regulators raised concerns about Negotiation Strategies in the context of onboarding. Their preliminary finding is that the project manager failed to secure firm commitments from functional managers for high-demand technical specialists during the planning phase, leading to a 20% delay in the initial project milestones. When renegotiating these resource allocations to align with the Resource Management Plan, which approach should the project manager prioritize to ensure a sustainable agreement that satisfies all stakeholders?
Correct
Correct: In project management, a collaborative or win-win negotiation strategy is preferred because it focuses on interest-based bargaining. By exploring the needs of both the project (timely delivery) and the functional managers (resource stability for other tasks), the project manager can develop creative solutions that satisfy both parties. This leads to stronger commitment and reduces the likelihood of future resource withdrawals, which is critical for long-term project success and stakeholder alignment.
Incorrect: A competitive strategy often creates a win-lose dynamic that can damage long-term professional relationships and lead to retaliation or lack of support in future phases. An accommodating strategy, while maintaining harmony, may leave the project without the necessary resources to meet its objectives, effectively failing the project’s charter. A compromise strategy, though common, often results in a ‘lose-lose’ outcome where neither party’s needs are fully met, potentially leading to mediocre performance and unresolved underlying issues.
Takeaway: Effective project negotiation should prioritize collaborative, interest-based outcomes to ensure sustainable stakeholder buy-in and optimal resource allocation.
Incorrect
Correct: In project management, a collaborative or win-win negotiation strategy is preferred because it focuses on interest-based bargaining. By exploring the needs of both the project (timely delivery) and the functional managers (resource stability for other tasks), the project manager can develop creative solutions that satisfy both parties. This leads to stronger commitment and reduces the likelihood of future resource withdrawals, which is critical for long-term project success and stakeholder alignment.
Incorrect: A competitive strategy often creates a win-lose dynamic that can damage long-term professional relationships and lead to retaliation or lack of support in future phases. An accommodating strategy, while maintaining harmony, may leave the project without the necessary resources to meet its objectives, effectively failing the project’s charter. A compromise strategy, though common, often results in a ‘lose-lose’ outcome where neither party’s needs are fully met, potentially leading to mediocre performance and unresolved underlying issues.
Takeaway: Effective project negotiation should prioritize collaborative, interest-based outcomes to ensure sustainable stakeholder buy-in and optimal resource allocation.
-
Question 8 of 10
8. Question
The operations team at an audit firm has encountered an exception involving Source Selection Criteria during periodic review. They report that during the procurement phase of a high-security data migration project scheduled for the upcoming fiscal year, the project manager weighted Technical Expertise at 70 percent and Price at 30 percent. However, the internal audit found that the criteria failed to account for the vendor’s long-term financial stability, despite the project duration exceeding 24 months. The procurement department is now questioning the validity of the current vendor shortlist. What should the project manager do to ensure the source selection criteria are robust and aligned with organizational risk standards?
Correct
Correct: Source selection criteria are developed during the Plan Procurement Management process and are used to rate or score seller proposals. For long-term projects, financial capacity is a critical component of these criteria to ensure the vendor can sustain operations and support the project through its entire lifecycle. Updating the criteria to include this factor ensures that the selection process is aligned with the project’s risk profile and organizational standards.
Incorrect: Including a performance bond later is a risk mitigation strategy but does not correct the flawed selection process that failed to evaluate vendor viability initially. Increasing the price weighting is an arbitrary change that does not directly measure or guarantee financial stability. Requesting a waiver ignores a legitimate risk identified by the audit team and undermines the governance and quality of the procurement process.
Takeaway: Source selection criteria must be comprehensive and tailored to specific project risks, such as ensuring vendor financial stability for long-duration contracts.
Incorrect
Correct: Source selection criteria are developed during the Plan Procurement Management process and are used to rate or score seller proposals. For long-term projects, financial capacity is a critical component of these criteria to ensure the vendor can sustain operations and support the project through its entire lifecycle. Updating the criteria to include this factor ensures that the selection process is aligned with the project’s risk profile and organizational standards.
Incorrect: Including a performance bond later is a risk mitigation strategy but does not correct the flawed selection process that failed to evaluate vendor viability initially. Increasing the price weighting is an arbitrary change that does not directly measure or guarantee financial stability. Requesting a waiver ignores a legitimate risk identified by the audit team and undermines the governance and quality of the procurement process.
Takeaway: Source selection criteria must be comprehensive and tailored to specific project risks, such as ensuring vendor financial stability for long-duration contracts.
-
Question 9 of 10
9. Question
A regulatory inspection at an audit firm focuses on Negotiation Strategies in the context of complaints handling. The examiner notes that during the planning phase of a new digital intake system, the Project Manager and the Chief Compliance Officer are in disagreement over the mandatory data fields required for initial submissions. The Compliance Officer insists on 25 mandatory fields to ensure data integrity, while the Project Manager argues that this will increase user abandonment rates by 40% based on pilot testing. To reach an optimal resolution that balances regulatory thoroughness with system usability, the Project Manager initiates a negotiation. Which strategy is most appropriate for achieving a win-win outcome in this scenario?
Correct
Correct: Collaborative negotiation, also known as integrative bargaining or problem-solving, is the most effective strategy for achieving a win-win outcome. It involves parties working together to identify the underlying interests behind their positions and finding creative solutions that satisfy both sets of needs. In this scenario, the Project Manager addresses the Compliance Officer’s need for data integrity and the project’s need for usability by redesigning the process rather than simply trading off one for the other.
Incorrect: Compromising is often considered a lose-lose or sub-optimal strategy because both parties give up something, potentially resulting in a system that is neither fully compliant nor fully usable. Accommodating (or smoothing) prioritizes the relationship over the project’s functional goals, which may lead to a system that users reject. Forcing (or competing) uses power or authority to resolve the conflict, which can damage stakeholder relationships and lead to long-term resistance or project failure.
Takeaway: Collaborative negotiation is the preferred project management approach for resolving stakeholder conflict as it seeks to maximize value for all parties by focusing on interests rather than fixed positions.
Incorrect
Correct: Collaborative negotiation, also known as integrative bargaining or problem-solving, is the most effective strategy for achieving a win-win outcome. It involves parties working together to identify the underlying interests behind their positions and finding creative solutions that satisfy both sets of needs. In this scenario, the Project Manager addresses the Compliance Officer’s need for data integrity and the project’s need for usability by redesigning the process rather than simply trading off one for the other.
Incorrect: Compromising is often considered a lose-lose or sub-optimal strategy because both parties give up something, potentially resulting in a system that is neither fully compliant nor fully usable. Accommodating (or smoothing) prioritizes the relationship over the project’s functional goals, which may lead to a system that users reject. Forcing (or competing) uses power or authority to resolve the conflict, which can damage stakeholder relationships and lead to long-term resistance or project failure.
Takeaway: Collaborative negotiation is the preferred project management approach for resolving stakeholder conflict as it seeks to maximize value for all parties by focusing on interests rather than fixed positions.
-
Question 10 of 10
10. Question
During a periodic assessment of Conduct Procurements as part of market conduct at an audit firm, auditors observed that for a critical software implementation project valued at $500,000, the project team bypassed the formal proposal evaluation committee. Instead, the project manager selected a vendor based on a previous successful relationship, despite the procurement management plan requiring a weighted scoring model for all contracts exceeding $100,000. Which action is most appropriate for the auditor to recommend to address this process deviation?
Correct
Correct: The Conduct Procurements process requires that proposals be evaluated against the source selection criteria established during the planning phase. Using a weighted scoring model ensures objectivity and transparency. If a deviation occurs, the correct corrective action is to apply the intended controls to ensure the best vendor was indeed selected according to the project’s requirements and to maintain the integrity of the procurement process.
Incorrect
Correct: The Conduct Procurements process requires that proposals be evaluated against the source selection criteria established during the planning phase. Using a weighted scoring model ensures objectivity and transparency. If a deviation occurs, the correct corrective action is to apply the intended controls to ensure the best vendor was indeed selected according to the project’s requirements and to maintain the integrity of the procurement process.